Carter Drive Flood Alleviation Scheme
Clients: Enterprise and Thames Water
Duration: 32 weeks
Location: Carter Drive,Collier Row, Essex
Description of works:
M&A Roarty Construction, on behalf of Enterprise constructed a
concrete segmental caisson shaft storage tank, 15m diameter
21m deep.
The project also included:
Construction of approximately 1350m of 450mm dia. pipe in open
cut at depths to invert of up to 3.0m.
Construction of approximately 17m of 375mm dia. pipe in open
cut maximum depth to invert 3.0m.
Construction of approximately 25 number associated manholes /
chambers maximum size 2000mm (internal) and maximum depth 3.0m.
|