Farm Road Flood Alleviation Scheme


Clients: Enterprise and Thames Water 

Duration: 26 weeks 

Location: Farm Road, Edgeware, NW London

Description of works: 

M&A Roarty Construction, on behalf of Enterprise constructed 
306m of 1500mm sewer by fully mechanised Pipejack tunnelling machine.

The project also included: 

2 No. 4m dia underpinned shafts approx 10m deep
3 No. 3m dia shafts approx 8m deep
30m of 900 pipe installed in 1.5m x 1.5m timber heading
150m 300mm rider sewer in open cut ave depth 2.6m
50m 1500mm sewer in open cut ave depth 2.2m
Various ancillary manholes

              
                          
                          
                                          

back to top

button; link to our Frimley excavation project page
button; link to our Grove Vale project page
button; link to our A13 project page
button; link to our DMR Main Laying project page
button; link to our Moorgate project page

 

 


M&A Roarty Construction™, roartyconstruction.com™, & roartyconstruction.co.uk™ are registered trademarks. Site content ©2005-2007
.
All Rights Reserved Rocket Web Design.

This site has been produced by Rocket Web Design.